Just received this letter in the mail. Looks like it will be another noisy, disruptive weekend. We have listed some of the important information below:

N Judah Shutdown Sept 14th - 17th

Construction begins Friday Sept 14th 7pm to Monday Sept 17th 5am and will continuously work around the clock. (oy)

Work that going to be done during the shutdown:
  • concrete placement of the tracks near Sunset Tunnel (east of Cole)
  • JACKHUMMERING
  • manhole removal and concrete repair
  • trolley pole construction 
  • more JACKHUMMERING


Street closures and parking restrictions:
  • no parking will be allowed on either side of Carl from Stanyan to Cole
  • driveways on the north side of Carl St from Stanyan to Cole will be blocked by construction for the duration of the shutdown.
  • no parking on Carl St for approx 150ft in both directions of 375 Carl (between Hillway and Willard)
  • no parking will be allowed on Carl St for approx 250ft east of Cole St.



Got Questions?! SHIMMICK Construction has gladly given you their phone number if you have any questions or concerns. 
Jeremiah Kent (Project Manager): 510-817-0729


Got photos or complaints? Share them with us all this coming weekend on Twitter by using the hastag #sfmtacarl! 


 
 
So construction is beginning, many of you might have seen the no parking signs, construction trucks, etc. Seems like they are prepping for weekends upon weekends of construction. Looks like the first set of weekend constructions are set to begin Feb 24th, below is more details regarding timing and type of construction. Remember, we are all in this together! Hopefully it won't be too horrible.

Share your stories, your noise complaints, and your photos of this project and how it affects you. Humorous pictures and stories highly encouraged! colevalleysf.webmaster@gmail.com, tell us on twitter @colevalleysf #sfmtacarl or on our tumblr


February 24th 7pm until February 27th 5am
       Sewer work on Carl between Arguello and Hillway Ave (south side)
       Sewer work on Carl between Stanyan and Shrader (south side)

March 2nd 7pm until March 5 5am
       Sewer work on Carl between Arguello and Willard (south side)
       Sewer work on Carl between Stanyan and Shrader (south side)

March 9th 7pm until March 12th 5am
       Track and sewer work on Carl between Arguello and Willard (center)
       Track and sewer work on Carl between Stanyan and Shrader (south side)

March 16th 7pm until March 19th 5am
       Track and sewer work on Carl between Arguello and Willard
       Track and sewer work on Carl between Stanyan and Shrader

March 23rd 7pm until March 26th 5am
      Track and sewer work on Carl between Hillway and Willard
      Track and sewer work on Carl between Shrader and Cole Street

March 30th 7pm until April 2nd 5am
     Track and sewer work on Carl between Hillway and Willard (including Willard intersection)
     Track and sewer work on Carl between Shrader and Cole Street

SFMTA wants to make note that all schedules are subject to change due to weather or unexpected conditions.

N Judah Shut-down 
So the N Judah Muni line will be shut down and replaced with a bus shuttle service from Ocean Beach to Church Street. The N Line will not operate in the subways, however there will be a supplemental rail service between Castro Station and Caltrain Station. These adjustments will begin approximately 7pm Fridays until 5am Mondays.

There will also be longer partial shutdowns of the J Line and a full shutdown of the N line beginning May 25th. The N Owl, 22 Fillmore, 37 Corbett and 43 Masonic will also be rerouted.

Note to Residents and Merchants
Residents and merchants can expect bike lane closures and detours during construction. Traffic control officers and police will direct traffic at critical intersections. There will also be electronic messaging. Access to local businesses, residences and driveways will be maintained. Updates will be given on an ongoing basis.

For more information and updates check out: www.sfmta.com/carl
 
 
So on November 9th 2011, the SFMTA had a community outreach meeting at Grattan Elementary School to talk about the Carl Street Rail Replacement Project. The meeting talked about the project limits, time frame, and budget, among other things. So, I know what you're thinking. Will muni stop running? I live on Carl, does that mean I'm stuck with loud construction noises and no street parking? Hopefully all these questions will be answered in time.

Here's the facts:

Project Limits: On Carl Street, between Cole and Arguello. 
Project Timeframe: Completion Estimated at February 2013!
Resident Inconvenience: A lot!
Muni Stoppage: You betcha!
Budget: $18.3 Million

Transit, Infrastructure and Streetscape Enhancements:
1. Muni light rail service improvements:
          -Safety
          -Reliability
2. Train lubricators to help mitigate noise and vibration from the train
3. Curb ramp upgrades
4. Water and sewer improvements
5. Pole replacements.

What to read the all the information about the Rail Replacement Project, we got you! Let us know (via Contact Us) with your email and we'll send you along the pdf. Thanks @njudah for passing the information to us!