Here's the facts:
Project Limits: On Carl Street, between Cole and Arguello.
Project Timeframe: Completion Estimated at February 2013!
Resident Inconvenience: A lot!
Muni Stoppage: You betcha!
Budget: $18.3 Million
Transit, Infrastructure and Streetscape Enhancements:
1. Muni light rail service improvements:
-Safety
-Reliability
2. Train lubricators to help mitigate noise and vibration from the train
3. Curb ramp upgrades
4. Water and sewer improvements
5. Pole replacements.